This is an example installing a 10kW Bergey wind turbine which I worked on with Ottawa Solar Power. The blades are 10 feet each making for 20 feet in diameter. The tower is over 100 feet high. Some of the work was done during the cold Ottawa winter.

The full wind turbine with solar arrays at its base.
The full wind turbine with solar arrays at its base.

This wind turbine uses a self-supporting tower. The alternative would be to attach guy-wires to the tower in order to hold it up. A self-supporting tower requires a massive base to keep the tower and wind turbine from falling over and is usually more costly than using guy-wires. However, a self-supporting tower typically looks more elegant than one using guy-wires. In this case, appearances were very important for the customer. For that reason you'll see details below about the big hole needed for the massive base and the concrete pouring of the base.

Digging the hole (December) - We were lucky to have very little snow in December. The hole for the base was dug, walls for the wooden form put up, and the cylindrical metal column that the tower would be bolted to, put in place. The last photo was taken in late January, awaiting the pouring of the concrete.

Hole dug for the concrete foundation for the wind turbine.
Hole dug for the concrete foundation.
The wooden form and metal column for the wind turbine.
The wooden form and metal column.
Covering the ground with a tarp.
Covering the ground with a tarp.
Everything covered in snow.
Everything covered in snow.

Pouring the concrete (February) - Since the concrete for the base was being poured in the middle of the winter, a warm building had to be built around it. The building was a temporary thing made of two-by-fours with orange tarp walls and roof. It was heated with construction heater, basically a large gas powered torch.

The tall concrete pouring truck arrived as seen in the first photo below. The orange tarp building can be seen just on the far side of the front of the truck, below the solar tower. Trucks bearing loads of concrete arrive and pour their concrete into the back of the concrete pouring truck, as shown in the second photo. The concrete is then sent up the tall tube and down into the tarp building.

One view of the tarp building.
One view of the tarp building.
Concrete truck delivering concrete.
Concrete truck delivering concrete.

Inside the tarp building you can see that the hole has been filled with rebar. The middle photo shows the concrete pouring hose snaking down from the roof. The last photo shows the guys directing the concrete into the rebar base.

The rebar covered floor inside the tarp building.
The rebar covered floor inside the tarp building.
Concrete being delivered by a hose to inside the tarp building.
Concrete being delivered by a hose.
The concrete being poured into the rebar.
Pouring the concrete.

A couple of weeks later the concrete is hardened enough that the orange tarp building is removed. A layer of snow now covers the concrete base with only the central column that the tower will be bolted to showing through. We wait for spring.

The snow-covered concrete  wind turbine's base.
The snow-covered concrete base.

Installing the tower and wind turbine (May) - The three column segments making up the tower, the wind turbine and its blades have all arrived. And so has a crane. The three column segments are each tapered like truncated cones. The first one is lifted and bolted into place. Then the second one is lowered over the first one. Being tapered, the top portion of the first one is actually inside the bottom portion of the second one and similarly for the top and middle ones.

Next, as the following photos show, while the crane holds the turbine body up, the wind vanes that will keep it turned into the wind are attached. Then the three 10 foot blades are bolted on. Someone then goes up the tower to help attach the wind turbine to the top of the tower and do the final connections.

There was enough wind that day that when we released the brake, done by releasing the shorted wiring (by a safe switch of course), the inverter quickly showed 8kW of output!

Wind vanes being attached to the wind turbine.
Wind vanes being attached to the turbine.
Blades being bolted to the wind turbine.
Blades being bolted to the turbine.
View of the crane.
The crane.
Tower with the wind turbine on the top.
Tower with the wind turbine on the top. A person is barely visible near the top.
Person near the top of the tower attaching the wind turbine.
Person near the top of the tower attaching the wind turbine.

The final result! - The first photo is from far in back of the property. The tower can be seen in the middle distance. The second photo shows the awesome sight from the front of the house. Who said wind turbines can't be a thing of beauty!

View of the wind turbine behind the house.
View of the wind turbine behind the house.
View of the wind turbine from far away.
View of the wind turbine from far away.
The full wind turbine with solar arrays at its base.
The full wind turbine with solar arrays at its base.

More topics

rimstar.org - Share your project on rimstar.org - About - Privacy policy - © 2020 Steven Dufresne
Contact: